ProdRoads documentation
Sprint and milestone setup
Right-click a calendar row and choose Edit Sprints or Edit Milestones.
Set the duration in weeks, choose whether numbering starts on the first Monday of the year or on a specific date, and decide whether numbering restarts each year.
The first period number can be customized. Changing the roadmap range recalculates first-Monday schedules from the first year in that range.
- Open Edit Sprints or Edit Milestones.
- Set the duration in weeks.
- Choose the starting rule or a specific date.
- Configure numbering and confirm.
See it in action
The example below edits the sprint schedule and applies the new settings to the production calendar.
Tip
Use a specific start date when the production cadence does not follow the first Monday of the year.